Draft Details

Designation:B79.2
Source:CSA
Review start date:Jul 9, 2021
Review end date:Sep 7, 2021
Contact email:mary.morgan(at)csagroup.org
Draft Scope/Description:

1.1 Inclusions

This standard covers cleanouts including floor and wall types used in concealed piping in and adjacent to commercial, industrial, institutional, and other buildings open to the public.

1.2 Terminology

In this Standard, “shall” is used to express a requirement, i.e., a provision that the user is obliged to satisfy in order to comply with the standard; “should” is used to express a recommendation or that which is advised but not required; and “may” is used to express an option or that which is permissible within the limits of the Standard.

Notes accompanying clauses do not include requirements or alternative requirements; the purpose of a note accompanying a clause is to separate from the text explanatory or informative material.

Notes to tables and figures are considered part of the table or figure and may be written as requirements.

Annexes are designated normative (mandatory) or informative (non-mandatory) to define their application.

You may comment on any section of this document by clicking the “Submit Comment” link at the bottom of the relevant section.